Minister of Works, Dave Umahi shakes hands with Dr. Lars Richter, Managing Director, Julius Berger Plc
Highlight

Contract variation: FG pays Julius Berger N20bln for Bodo-Bonny Road

"This is coming just as the minister suggested an additional N20 billion augmentation fee to the contractor to cushion the effects of current economic realities in the country"

526

The Federal Government says it has paid Julius Berger a N20 billion augmentation fee for the construction of the Bodo-Bonny Road.

The row between the federal government and Julius Berger Plc regarding the halting of construction on the N200 billion Bodo-Bonny Road in Rivers State appears to have been settled, with the government offering an extra N20 billion payment to the company.

Persecondnews recalls that Mr. Dave Umahi, the Minister of Works, issued a warning last Thursday that the federal government might reconsider its contract with Julius Berger if the company failed to resume work on the project within 14 days.

Julius Berger announced in a statement on Sunday that they have received an extra augmentation fee of N20 billion following a meeting between the minister and their Managing Director, Dr. Lars Richter.

The statement reads: “This is coming just as the minister suggested an additional N20 billion augmentation fee to the contractor to cushion the effects of current economic realities in the country.

“Umahi, who was of the view that there was no need for any augmentation, hoped that the additional amount of N20 billion, which he announced there and then, would assuage the contractor’s burden on the project.”

The minister, according to the statement, reminded the stakeholders of the importance of the project to both the surrounding communities and the country.

He added that when completed, the road would enhance development, even as he gave the assurance to Bonny Kingdom that the project would be completed by the end of 2024.

Richter drew the attention of the minister to the time lag when the contract was awarded in 2014 when the exchange rate was N305 to a dollar, adding that the cost of relevant construction materials had since risen by over 1000%.

He called for the variation of the contract, which he said has become necessary in view of the declining value of the naira and the rising cost of construction materials in the country.

“I thank you all for coming and for giving me this opportunity to shed more light on the project. Allow me to give you some insight from us on this project.

“This project was initiated in 2013, and today we are talking about 2024, which means the project is more than 11 years old. In 2014, we received the letter of award, but the project couldn’t commerce.

“Then in 2017/2018, the NLNG stepped in with the infrastructure tax credit scheme for modalities in funding the project,” he said.

Leave a comment

Related Articles

NNPC Ltd. hosts NSC boss, pledges support for revitalization of Nigerian football

In a significant move to boost Nigerian football, the Nigerian National Petroleum...

Nigerian youths essential to repositioning Africa, says VP Shettima

Vice President Kashim Shettima has reaffirmed the federal government’s commitment to youth...

Just in: Simon Ekpa ‘ll be extradited to Nigeria to face charges – Defence Headquarters

The Nigerian Defence Headquarters, Abuja, has announced plans to extradite Simon Ekpa,...

NPA’s CEO Dantsoho Makes History as First Nigerian Chairman of PMAWCA

In a groundbreaking achievement, Dr. Abubakar Dantsoho, Managing Director of the Nigerian...

Save for rainy day, Federal Accountant General urges state govts, emphasizes transparency, accountability

In a bid to ensure financial stability during adverse situations and economic...

Sacked UNIZIK VC Odoh to Tinubu: You can’t fire me through press release

Sacked Vice-Chancellor of Nnamdi Azikiwe University (UNIZIK), in Awka, Anambra State, Prof....

UBA to empower MSME’s with wealth management strategies at its ‘Built to Last’ series

As part of its commitment to deepen the growth and sustainability of...

Olopade assumes office as NSC DG, promises new lease of life for Nigerian sports

Bukola Olopade had assumed office as the Director General of the resuscitated...

Amid High Inflation Rate, IMF Pledges Support for Nigeria’s Economic Reforms

International Monetary Fund (IMF) President Kristalina Georgieva and her team met with...

Nigeria’s Super Falcons Ajibade, Nnadozie, Nominated for 2024 CAF Women’s Player of the Year

The Confederation of African Football (CAF) has announced the nominees for the...

Just in: FG announces reshuffle of governing councils at FUOYE, Kogi varsity

The Federal Government has made changes to the governing councils of Federal...

Exclusive: Eguavoen Opens Up on Declining NFF Contract Extension, Reveals Reasons

Super Eagles Coach, Austin Eguavoen, has revealed why he declined the Nigeria...

Boost for Nigeria’s Oil Production As NNPC’s Utapate Crude Grade Hits Global Oil Market

In a major boost for Nigeria’s crude oil production, revenue generation, and...

Just in: FG sacks varsity Pro-Chancellor for misconduct

The Minister of Education, Dr. Tunji Alausa, has announced the removal of...

Just in: INEC presents Certificates of Return to Ondo Gov. Aiyedatiwa, deputy

The Independent National Electoral Commission (INEC) has presented Certificates of Return to...

Breaking: Senate sacks Danladi Umar, Code of Conduct Tribunal chairman  

Following proven allegations of gross misconduct and unacceptable behaviour, the Senate on...

Just in: South Africa takes over G20 Presidency from Brazil, first African nation to lead the bloc

South Africa has taken over the presidency of the G20 from Brazil,...

Tinubu submits 3 INEC REC, federal commissioner-nominees for Senate’s approval

President Bola Tinubu has sent the name of Ondo Resident Electoral Commissioner,...

Just in: After a night in custody, DSS in Ogun releases Ladi Adebutu

Mr. Ladi Adebutu, the 2023 People’s Democratic Party (PDP) governorship candidate in...